Know Haryana Govt. – Kherki Daula Toll Bypass Timelines

1846
Know Haryana Govt. Kherki Daula Toll Bypass Timelines
Know Haryana Govt. Kherki Daula Toll Bypass Timelines

#KnowHaryanaGovt

Project: Kherki Daula Bypass
Length: 5 KM
Total Cost: 33.69 Crores
Purpose: Bypass Kherki Daula Toll and connect Faridabad, SPR to New Gurgaon Sec 81 to 115 inorder to give relief to the residents and commuters from traffic jams at Kherki Daula Toll.

Note: Copy of RTI where residents of 31 villages were exempted from paying toll however the residents and home buyers of New Gurugram are forced to pay toll everytime they cross Kherki Daula Toll. Download RTI

Various Deadlines and Milestones:
– First Proposed in Happening Haryana Global Investors’ Summit in 7-8 March’16
– Foundation Stone: 28 Aug’17
– Estimates sent to Chandigarh: 11 July’17
– First Timeline to Complete: Aug’17
– Work not Started till: 26 Dec’17
– Work Finally Started in Jan’18
– In Dec’17 new timelies to complete by Feb’18
– In Jan’18 new timelies to complete by April’18
– In Feb’18 new timeline to complete by June’18
– In June’18 new timeline to complete by July’18
– As on 8 June’18 400 Meter Stretch Still Incomplete due to sewage work going on in the area: Timeline Extended to July’18

Time Lapsed since:
– First proposed: 28 Months Lapsed
– Foundation stone by Mnister on 28 Aug’17: 11 Months Lapsed
– Start of Work: 7 Months Lapsed

July’18 will be over in few days however the Kherki Daula Bypass is still far from getting completed.

Supporting News and Tweets by Ministers:

26 March’16:
News: https://goo.gl/k1TKJ6

09 Sept’16
News: https://goo.gl/JpQzgE

24 Dec’16
News: https://goo.gl/LjbbPF

26 Jan’17
News: https://goo.gl/Hr5D66

1 May’17 (First Timeline to Complete: Aug’17)
News: https://goo.gl/JpZfHW

11 July’17 (Estimates sent to Chandigarh: 11 July’17)
News: https://goo.gl/LioUnc

29 Aug’17:
News: https://goo.gl/9eJLL4
Tweet from Minister: https://goo.gl/8afngR

26 Dec’17 (In Dec’17 new timelies to complete by Feb’18)
News: https://goo.gl/JwZRmT

22 Jan’18 (In Jan’18 new timelies to complete by April’18)
News: https://goo.gl/d9USRC

21 Feb’18 (In Feb’18 new timeline to complete by June’18)
Tweet from Minister: https://goo.gl/HwB1e7

March’18
Tweet from Minister: https://goo.gl/tuF928

8 June’18 (In June’18 new timeline to complete by July’18)
News: https://goo.gl/i37NYt
Tweet from Minister: https://goo.gl/eTgcTa

July’18 will be over in few days however:

  1. Kherki Daula Toll Bypass is still far from getting completed.
  2. Nor the Dwarka Expressway has been connected to NH48 properly,
  3. Kherki Daula Toll has not been removed after multiple assurances

Time and again Haryana Govt. has not been able to meet any of it’s promises mentioned above.

Does it take 28 months to complete 5 KM bypass road?